Montage Gold Reports on Its Q2 and H1-2025 Activities

Koné project construction on-budget and well on-schedule • Strong continued exploration focus • Robust liquidity sources

CONSTRUCTION ACTIVITIES

Over 3.0 million hours worked without a Lost Time Injury, with more than 2,500 employees and contractors on-site

Well on track for first gold pour in Q2-2027 and on budget with over $370 million of capital committed as at today, representing approximately 44% of the total capital expenditure, with prices in line with expectations

Rapid progress achieved on key process plant activities including the ball mill foundations, pre-leach and tailings thickeners, with notably the start of CIL tank erection occurring 2 months ahead of schedule which marks a key milestone

Other key infrastructure is well advanced including the river abstraction facility, TSF, relocation site, and plant buildings, while the water storage facility was completed and is already holding water

EXPLORATION ACTIVITIES

2025 exploration programme increased from 90,000 to 120,000 meters, with 83,280 meters already drilled in H1-2025, focused on delineating higher-grade resources with the goal of supplementing production from the onset

Step-out and in-fill drilling is underway at all 7 new higher-grade satellite deposits for which starter maiden resources were published in early 2025, whilst drilling progressed on the 6 targets which were advanced to pre-resource stage

Maiden resources for new discoveries and updated resources for the recently made discoveries are expected to be published throughout the year

FINANCIAL POSITION

Robust liquidity and available sources of financing totalling $735 million compared to remaining capital disbursements of $676 million

VANCOUVER, Canada, Aug. 12, 2025 (GLOBE NEWSWIRE) -- Montage Gold Corp. ("Montage" or the "Company") (TSX:MAU, OTCQX:MAUTF) is pleased to report on its construction and exploration activities for Q2-2025, with highlights provided in Table 1 below.

Table 1: Business and financial highlights

 

 

 

 

 

THREE MONTHS ENDED

SIX MONTHS ENDED

 

All amounts in $ million unless otherwise specified

June 30, 2025

March 31,2025

June 30,2024

June 30,2025

June 30,2024

Δ Q2-2025 vs. Q1-2025

CONSTRUCTION ACTIVITIES

 

 

 

 

 

 

Cumulative hours worked, million hrs 

2.7

 

1.0

 

-

 

2.7

 

-

 

+1.7

 

Lost-Time Injuries Frequency Rate, %

0.0

 

0.0

 

-

 

0.0

 

-

 

0.0

 

Total cumulative capital committed, inclusive of amount disbursed

339.2

 

217.5

 

-

 

339.2

 

-

 

+121.7

 

- Cumulative capital disbursed

158.8

 

84.6

 

-

 

158.8

 

-

 

+74.2

 

- Cumulative capital committed and to be disbursed

180.4

 

132.9

 

-

 

180.4

 

-

 

+47.5

 

EXPLORATION ACTIVITIES

 

 

 

 

 

 

Meters drilled, meters

37,393

 

45,887

 

20,543

 

83,280

 

20,543

 

(8,494

)

Exploration expenditure

6.4

 

6.9

 

3.9

 

13.3

 

5.8

 

(0.5

)

CASH FLOW AND LIQUIDITY POSITION1

 

 

 

 

 

 

Cash flows used in investing activities

(88.3

)

(56.7

)

(0.3

)

(145.0

)

(0.3

)

(31.6

)

Cash flows generated from financing activities

150.5

 

0.4

 

0.3

 

151.0

 

26.4